Hardening a historic federal building without touching the stone.

JS Global installed 121 AT/FP-rated storm windows in front of the existing historic windows of an occupied 750,000 SF federal building in Washington, DC, using non-invasive methods that left the original masonry intact.

121 storm
windows
  • Occupied historic building
  • About 750,000 SF
  • AT/FP-rated
Historic PreservationForce Protection
Project Overview

Security upgrades cannot cost a historic building its character.

The building was fully occupied, historically significant, and home to irreplaceable contents.

JS Global, as prime contractor, installed the AT/FP-rated storm windows in phases, working with preservation specialists, curators, and federal security staff. The team managed abatement, scaffolding, protection, and installation so that the building could keep operating while it was hardened.

Project Snapshot

The assignment at a glance.

LocationWashington, DC
FacilityOccupied historic federal building, about 750,000 SF
Project TypeAT/FP storm window installation
Scope121 AT/FP-rated storm windows
Primary ConstraintHistoric stone, occupants, and security controls
MethodNon-invasive frames, phased work
RolePrime contractor
The Challenge

Protect the stone, the contents, and the occupants at the same time.

01

Install AT/FP-rated windows without drilling into or scarifying the historic stone.

02

Work in phases inside a fully occupied building under strict security controls.

03

Remove asbestos-containing caulk from the stone joints under industrial hygiene oversight.

04

Keep priceless artwork and sculpture safe while construction went on nearby.

The Approach

Build the protection around the building, not into it.

  1. 01

    Coordinate

    Preservation specialists, curators, industrial hygienists, art-handling experts, and security staff shaped the plan from the start.

  2. 02

    Protect

    Temporary perimeter walls and protective barriers separated work areas from occupants and contents, and artwork was relocated under controlled conditions.

  3. 03

    Abate

    Qualified subcontractors removed asbestos-containing caulk from the stone joints under an on-site industrial hygienist.

  4. 04

    Access

    Engineered scaffolding with overhead protection, plus custom lifting equipment including a suction lifter, handled the oversized glass units.

  5. 05

    Install

    Frames were mounted without drilling or scarifying the stone, with extra care around arches and keystone details.

The Result

Stronger protection, original stone intact.

01

121 AT/FP-rated storm windows now sit in front of the building’s historic windows.

02

The original masonry stayed intact because the frames were installed without drilling.

03

Work continued in a fully occupied building under phased, security-controlled access.

04

The added layer of glass also gives the building an extra layer of insulation.

What Made It Work

Preservation and security were planned together.

Neither requirement was allowed to override the other.

Preservation specialists, security staff, curators, and installers worked from the same phased plan, so protection for the building and its contents was part of every phase of the work.

Project Questions

Hardening historic buildings in use.

Practical answers about protecting stone, contents, and occupants during a security upgrade.

01Were the original windows removed?
No. The AT/FP-rated storm windows were installed in front of the existing historic windows.
02How was the historic stone protected?
Frames were installed with non-invasive methods, with no drilling or scarifying of the stone. Openings were prepared with extra care around arches and keystone details.
03Could the building stay in use during the work?
Yes. Work was phased and security-controlled, with some tasks scheduled at night to limit disruption to occupants.
Plan the Protection Early

Hardening a historic or occupied building?

Share the building’s use, preservation constraints, security requirements, and schedule limits. JS Global will help plan a path that protects both the mission and the structure.